The schedules are for the construction of two different buildings: a residential independent building and a residential (S+5) building. The chart outlines the different activities that need to be completed for each project, as well as the duration of each activity.
The chart also includes some basic tips for scheduling, such as the fact that the schedules can be planned between 6-8 months or 12-15 months, depending on the resources available. The chart also notes that the activities can overlap each other, which can help to reduce the overall project timeline.
Here is a more detailed analysis of the chart:
- Residential independent building: This project is scheduled to take a total of 8 months to complete. The longest activity is the sub structure, which is scheduled to take 3 months. The other activities are all scheduled to take 1 month each.
- Residential (S+5) building: This project is scheduled to take a total of 15 months to complete. The longest activity is the super structure, which is scheduled to take 4 months. The other activities range in duration from 1 month to 3 months.
As you can see, the residential (S+5) building is a much larger and more complex project than the residential independent building. This is reflected in the fact that the (S+5) building has a longer overall timeline and longer durations for each activity.
It is important to note that these are just basic schedules, and the actual duration of each project could vary depending on a number of factors, such as the availability of resources, the weather, and any unforeseen challenges that may arise.
Overall, the chart provides a helpful overview of the basic steps involved in constructing two different types of buildings. It is important to remember that these are just estimates, and the actual scheduling of a construction project can be quite complex.